2024
Stage 1
May
USF issues public Stage 1 Intent to Negotiate (ITN) for potential master developers
Stage 2
Sept.
USF selects most qualified candidates to proceed to Stage 2 of the ITN, during which they submitted proposals
-
2025
Partners Selected
Feb.
USF selects P3 Partners
FL BOG Submission
Aug. 7
Project Information submitted to Florida Board of Governors
FL BOT Presentation
Aug. 22
Project presented to USF Board of Trustees Finance Committee
USF BOT VOTE
Sept. 9
USF Board of Trustees approves resolution
FL BOG VOTE
Nov. 6
Florida Board of Governors approves the project
-
2026
Construction Begins
2026
Phase one construction begins
-