Project Timeline

  1. 2024

    1. Stage 1

      May

      USF issues public Stage 1 Intent to Negotiate (ITN) for potential master developers

    2. Stage 2

      Sept.

      USF selects most qualified candidates to proceed to Stage 2 of the ITN, during which they submitted proposals

  2. 2025

    1. Partners Selected

      Feb.

      USF selects P3 Partners

    2. FL BOG Submission

      Aug. 7

      Project Information submitted to Florida Board of Governors

    3. FL BOT Presentation

      Aug. 22

      Project presented to USF Board of Trustees Finance Committee

    4. USF BOT VOTE

      Sept. 9

      USF Board of Trustees approves resolution

    5. FL BOG VOTE

      Nov. 6

      Florida Board of Governors approves the project

  3. 2026

    1. Construction Begins

      2026

      Phase one construction begins

  4. 2028

    1. Student Housing Opens

      Aug.

      Student housing becomes operational as part of Phase 1 of the project